New Offices, Plot C

Location:Farnborough Business Park

Principal Contractor: Kier

Engineer

Engineer: Baynham Meikle


Engineer

Disciplines Undertaken:
Structural Steelwork, Metal decking, Edge Protection, Pre cast concrete stairs


Tonnage

Tonnage: 850


Cost

Value: £1,600,000


We were contracted to supply and install the steelwork for two Grade A offices at Plot C Farnborough Business Park; providing 108,000 sq. ft of new office space.

We were tasked with the supply and installation of 12,000m2 of metal decking, installation and temporary edge protection which was installed at ground level to provide a safe working working edge around the structure and during the installation of pre cast concrete staircases.

The programme of the scheme was a critical element for our our client; therefore we supplied a number of erection teams to allow both buildings to be constructed at the same time. As a result of this we delivered the scheme including the metal decking aspects within their exacting timescale.

Erecting the steel Erecting Steel 2 Steel erection with edge protection taking shape finished building
  • Erecting the steel
  • Erecting Steel 2
  • Steel erection with edge protection
  • taking shape